Buitreras-Esquel Aqueduct

Project
Final Design for the Construction Project
Location
Esquel, Chubut, Argentina

Details

The main objective was to prepare the detailed design and the bidding documents to expand the drinking water supply in the town of Esquel, Chubut. Design work was carried out that included the construction of intake structures on the Buitreras and Percy watercourses, the interconnection with a pumping station, and the review and update of designs for aqueducts and storage tanks.

In addition, a feasibility study was conducted to determine the optimal location for the intake structure, followed by the preparation of the detailed design for a 13-km aqueduct and the evaluation of various route options and intake points.

ConsulTech

Do you need advice?

✕
Alvear 360, Pigüé